OUR TWIN DUPLEX @ ROYAL HAVEN ESTATE ABIJO GRA LAGOS IS ALMOST COMPLETED.
SITE WORK UPDATE
? Foundation work - Done
? Ground floor work - Done.
? First Floor Block work - Done.
? First Floor lintel - Done.
? First Floor Decking - Done.
? First Floor block work - Done.
? Iron Work For Concrete Work - Done
? Electrical Work - Ongoing.
? Plumbing Work - Ongoing
? Scaffolding Work In Preparation for Parapet Plastering Work - Ongoing.
? Internal Plastering Work - Ongoing.
? Roofing Wood Work - Ongoing.
DECEMBER 2019 COMMISSIONING DATE ON COURSE.
STILL SELLING @10.5m/600SQM OUTRIGHT